Nobu Danang construction site closed July with a series of key items completed for the project "a new lifestyle symbol of Da Nang city", including: the anti-shoring system of Tunnel B1 has been 100% completed, the excavation work of Tunnel B2 has reached 70%, the construction of steel reinforcement - pouring concrete for columns and walls of Tunnel B1 has reached 70% and 65% respectively. At the same time, items such as pile head treatment, waterproofing, and construction of the foundation of Tunnel B2 are also being accelerated every day. Each step of completion is a part of the foundation for the symbolic project of Da Nang - where the standard of luxury living will be gradually shaped.
Let's take a look at the upcoming plans on the journey to create the iconic Nobu Danang project:
Implementing excavation and shoring system for the B2 elevator foundation area
Complete cutting and chiseling of Barrette pile heads, pouring concrete lining and HDPE waterproofing membrane

Construction of steel reinforcement, formwork and pouring concrete for foundation, floor, water tank - wastewater treatment tank of Basement B2

Construction of 1st floor columns and walls started
We will continue to update you with the latest information on construction progress on the official website of the Nobu Danang project.
**According to the investor's update progress
DANANG VILLA REALTY


Please contact us
Please click the icons below to add us
as friends and contact us afterwards.
We also offer meetings through
Zoom or Google Meet upon request.
Languages available:
Japanese, English, Vietnamese.